Basic Info.
Output Type
AC Three Phase
Type
Horizontal Hydro Generator
Bearing Support
Radial Bearing or Radial Thrust Bearing
Regulation Work
7000-18000 Kgm
Product Description
Bulb Tubular Type water Turbine generator
Bulb turbine is one kind of units that fits for low-head and middle-large-Capacityconditions.
The unit has high efficiency and compact structure. We can provide the turbine units with diameter of runner≥3m.
Bulb type turbine reference | Governor | Transmission |
|
Type | Head(m) | Discharge (m3/s) | Speed(rpm) | Power(kW) | Regulation Work (kgm) |
|
|
1250a | | | | | | |
GZ1250a-WP-300 | 3.0-10 | 39.6-80.84 | 136.36-187.5 | 1319-5297 | 5000-12000 | Directly coupling |
GZ1250a-WP-330 | 3.0-10 | 46.5-101.2 | 115.4-150 | 1699-6745 | 5500-15000 | Directly coupling |
GZ1250a-WP-350 | 3.0-10 | 58.6-113 | 107.1-150 | 2140-7506 | 7000-18000 | Directly coupling |
GZ1250a-WP-370 | 3.0-10 | 69.5-128.5 | 100-150 | 2663-8489 | 8500-21000 | Directly coupling |
GZ1250a-WP-410 | 3.0-10 | 68.5-156.2 | 100-136.4 | 3399-10584 | 12000-26000 | Directly coupling |
GZ1250a-WP-450 | 3.0-10 | 111.2-1899 | 88.2-125 | 4238-12955 | 15000-33000 | Directly coupling |
995 | | | | | | |
GZ995-WP-300 | 6.0-15 | 46.1-97.8 | 150-214.3 | 3400-10650 | 7000-18000 | Directly coupling |
GZ995-WP-330 | 6.0-15 | 57.8-122 | 150-187.5 | 4264-13242 | 10000-23000 | Directly coupling |
GZ995-WP-350 | 6.0-15 | 72.5-142 | 125-187.5 | 5348-16020 | 12000-29000 | Directly coupling |
GZ995-WP-370 | 6.0-15 | 92.4-151 | 125-166.7 | 6744-17035 | 16000-31000 | Directly coupling |
GZ995-WP-410 | 6.0-15 | 110-188 | 115.4-166.7 | 8576-21209 | 20000-40000 | Directly coupling |
GZ995-WP-450 | 6.0-15 | 137.3-230.9 | 107.1-150 | 10705-26049 | 26000-52000 | Directly coupling |
GZ995-WP-600 | 6.0-15 | 150-298 | 60-125 | 12500-36000 | 32000-65000 | Directly coupling |
Company
Our company is an experienced manufacture and engineering Company in small scale hydro power equipment ( 100Kw to 50Mw). We play the role of manufacture and EPC contractor and could supply water to wire equipments and services. As turbine manufacture more than 60 years experience.
Our factory occupies 200,000 square meters of land, which includes 9 workshops, over 120 sets of heavy and precision producing and testing machinery; scientific research development center in the southern China, and various testing facilities. We have a general technical staff of 320 and 85 senior technical professionals.
We provide customers with the complete package, from the design and manufacture of the turbine, generator and control equipment through to installation, commissioning and ongoing repair and maintenance.
1.Water Turbine Generator Unit Design & SUPPLY
2.Hydropower equipment supply
3.Feasibility study of hydropower project
4.Manufacture
5.Installation & Supervision
6.Commissioning and Training service
7. Hydro power plant rehabilitant
8. Hydro power plant spares supply
9.Services
Our Services
Usually we guide the installation. We will dispatch engineers to site.(electrical engineer, mechanical engineer, control engineer and a translator according to requirement)
1.Water head:___M
2.Water flow:____M3/s
3.Frequency: 50HZ/60HZ
4.Generator outgoing line voltage:__Kv
5.On-grid or Off-grid type? (On-grid type voltage:____Kv)
Experience List (Part)
No. | Name of Projects | Turbine Type | Capacity | Year | Generator model |
1 | Yangdun hydropower station in jiaou,Fujian province | GDB3-WS-355 | 4×2500KW | 2005 | SFW2500-8/1730 |
2 | Gongba Heke hydropower station project in longnan,Gansu province | GZB14-WP-340 | 3×6000KW | 2014 | SFWG6000-40/3700 |
3 | Zhengdong hydropower company in Nanpin,Fujian province | GDB3-WS-335 | 2×1250KW | 2006 | SF1250-10/1730 |
4 | Qingshan pump station upgrading project in Changde city,Hunan province | GD008-WZ-295 | 3×2500KW | 2009 | SFW2500-8/1730 |
5 | Nanzhou hydraulic Co.,LTD.Huashizi hydropower station in Chongqing city | GZY310-WP-290 | 2×1600KW | 2014 | SFWG1600-40/2360 |
6 | Lianhuashan hydropower station in Wuyishan city | GDB3-WS-290 | 2×1500KW | 2011 | SFW1500-10/1430 |
7 | Guodian electric power development co., LTD sanjianfang | GZY320-WP-275 | 3×3000KW | 2010 | SFWG3000-32/3260 |
8 | Yaolaitan hydropower Co.,LTD in Tongdao county | GD008-WZ-275 | 4×1850KW | 2005 | SFW1850-8/1430 |
9 | Meixi hydropower station in Changtin county,Fujian province | GD006-WZ-275 | 2×2500KW | 2003 | SFW2500-8/1730 |
10 | Chuanneng electric power Co.,LTD in Fujian province | GD008-WZ-260 | 4×1250KW | 2006 | SFW1250-8/1430 |
11 | Shubu hydropower station In Lintan county,Gansu province | GD008-WZ-260 GZ008-WZ-260 | 2×2000KW 1×2000KW | 2006 | SFW2000-8/1430 |
12 | Shangba hydropower station in Ruyuan county,Guangdong province | GD008-WZ-260 | 2×630KW | 2005 | SFW630-8/1180 |
13 | Liucunba hydropower station in Ningguo county Anhui province | GD008-WZ-260 | 2×2000KW | 2003 | SFW2000-6/1430 |
14 | Cenggong Xinxin hydropower station in Guizhou province | GDB-WS-250 | 3×630KW | 2005 | SFW630-10/1180 |
15 | Yuanzhongxia hydropower station in Guizhou province | GDB-WS-250 | 3×630KW | 1997 | speed up |
16 | Dujiawan hydropower station in Yongdeng county,Gansu province | GDY269-WZ-245 | 3×1600KW | 2008 | SFW1600-32/2150 |
17 | Chunzhou hydropower station in Yangchun city,Guangdong province | GDY269-WZ-245 | 4×1250KW | 2007 | SFW1250-8/1430 |
18 | Sanlan Hezha hydropower station in Jieyang city,Guangdong province | DY269-WZ-240 | 4×630KW | 2008 | SFW630-44/2150 |
19 | Jianghua Jianqiao hydropower Co.,LTD in Hunan Province | GD006-WZ-240 | 4×3200KW | 2005 | SFW3200-8/1730 |
20 | Yunhe hydropower development Co.,LTD in Hunan province | GD008-WZ-240 | 3×1600KW | 2005 | SFW1600-8/1430 |
21 | Jianghua hydropower station in Hunan province | GD007-WZ-225 | 2×3200KW | 2002 | Straight league |
22 | Taifeng industrial Co.,LTD in Guangan city,Sichuan province | GD008-WZ-225 | 1×1600KW | 1996 | speed up |
23 | Xihetan hydropower station in Heilongjiang province | GDB-WS-225 | 10×2000KW | 1990 | speed up |
24 | Riyan hydropower station in Hunan Province | GD008-WZ-220 | 2×800KW | 2006 | speed up |
25 | Xiangtang hydropower station(first stage) project in Xiushan county,Chongqin city | GDY269-WZ-215 GDY269-WZ-155 | 2×800KW 1×400KW | 2010 | speed up |
26 | Nacha hydropower station in Zhan county,Hainan province | GD004-WZ-200 | 4×320KW | 1993 | speed up |
27 | Sanjiangbi hydropower station in Guangxi province | GD004-WZ-200 | 3×630KW | 1992 | speed up |
28 | Banzhong hydropower station in Fuan county,Fujian province | GDB-WZ-200 | 2×200KW | 1990 | speed up |
29 | Bailongshan hydropower station in Qianxi county,Hebei province | GDB-WZ-200 | 3×1600KW | 1988 | speed up |
30 | Hepu hydinceropower station in Guangxi Province | GDB-WZ-200 GD004-WZ-200 | 2×1250KW 1×1250KW | 1983 | speed up |
31 | Maonan hydropower station in Guangdong province | GDB-WS-190 | 3×160KW | 1994 | speed up |
32 | Maonan Maomin hydropower station in Guangdong province | GDB-WS-190 | 2×160KW | 1989 | speed up |
33 | Lanheba hydropower station in Gaozhou county,Guangdong province | GDB-WS-190 | 4×320KW | 1988 | speed up |
34 | Xinfupin hydropower station in Pintan county,Fujian province | GDB-WS-190 | 4×1250KW | 1986 | speed up |
35 | Huihuang hydropower station in Gansu province | GDY269-WZ-180 | 1×800KW | 2015 | SFW800-28/2150 |
36 | Zuojiawan hydropower station in Hanzhong city,Shanxi Province | GD007-WZ-180 GD007-WZ-140 | 2×2000KW 2×1250KW | 2013 | Straight league |
37 | Jimeiba hydropower station in Guangdong province | GD004-WS-180 | 3×2000KW | 1994 | speed up |
38 | Ancient Yellow river key water-control project in Huaian city | GD-WS-175 | 6×160KW | 2011 | SFW160-8/740 |
39 | Jianfen hydropower station in Hanzhong city,Shanxi province | GDB3-WS-165 | 2×630KW | 2006 | speed up |
40 | Xiaojiaohe hydropower station in Lintao county,Gansu province | GDB3-WS-165 | 3×500KW | 2006 | altitude1900 |
41 | Kuitunhe First hydropower station in Xinjiang Province | GT007-WZ-160 | 3×1250KW | 2014 | SFW1250-20/2150 |
42 | Yunxi hydropower station upgrading project in Jiangsu province | GDHGL-01-WS-160 | 10×200KW | 2013 | speed up |
43 | Funing and Xiaozhongzha hydropower station in South-to-North Water Diversion Project | GDB-WS-160 ZDT03-LM-100 | 7×250KW 1×100KW | 2011 | SFW200-6/740 SF100-6/560 |
44 | Shangtan hydropower station in Pinan county,Qinghai Province | GD006-WZ-160 | 3×1250KW | 1998 | altitude2200 |
45 | Yanghetan hydropower station in Jiangsu province | GD B-WS-160 | 3×160KW | 1995 | speed up |
46 | Xile hydropower station in Linan City,Zhejiang province | GD004-WS-160 | 5×630KW | 1991 | speed up |
47 | Guiling hydropower station in Shunchang City,Fujian province | GD004-WS-160 | 4×630KW | 1991 | speed up |
48 | Yundong hydropower station in Huaian city,Jiangsu province | GD004-WS-160 | 10×200KW | 1990 | speed up |
49 | Hunan mechnical and electrical irrigation equioment company | GD B-WZ-160 | 2×1600KW | 1988 | speed up |
50 | Yangzhuangzha hydropower station in Jiangsu province | GDB-WS-160 | 2×200KW | 1988 | speed up |
51 | Funing hydropower station in Yancheng city,Jiangsu province | GD760-WS-160 | 7×630KW | 1988 | speed up |
52 | Gaoshang hydropower station in Zijin county in Guangdong province | GD004-WS-160 | 3×200KW | 1988 | speed up |
53 | Cenxi hydropower station in Guangxi province | GD004-WZ-160 | 3×320KW | 1988 | speed up |
54 | Kuidou hydropower station in Anxi city,Fujian province | GD004-WZ-160 | 3×200KW | 1986 | speed up |
55 | Yunxi hydropower station in Huanan city,Jiangsu province | GD004-WS-160 | 10×200KW | 1983 | speed up |
56 | Gaoliangjian hydropower station in Hongze county,Jiangsu province | GD760-WZ-160 | 16×200KW | 1971 | speed up |
57 | Yachong hydropower station in Hainan province | GDY269-WZ-140 GTY269-WZ-140 | 2×360KW 1×360KW | 2015 | |
58 | Yamutan pump station upgrading project in Sanming City | GD006-WZ-140 | 4×800KW | 2013 | |
59 | Entumake hydropower station in Kazakhstan | GD006-WZ-140 | 1×630KW | 2009 | Straight league |
60 | Jijiahe hydropower station in Lintao county ,Gansu province | GDB3-WS-140 | 4×500KW | 2006 | altitude1900 |
61 | Gufengqu hydropower station in Honggu county Gansu province | GDy269-WZ-130 | 3×350KW | 2010 | |
62 | Xiajia hydropower station of Linyun power station subsidiary company in Guangxi province | GD007-WZ-130 | 2×1000KW | 2007 | Straight league |
63 | Youcheng hydropower Company in Wuyishan city,Fujian province | GD008-WZ-120 | 2×500KW | 2005 | Straight league |
64 | harbin electrical machinery plant ordering) | GD007-WZ-120 | 2×500KW | 2005 | Straight league |
65 | Fuchun Industrial development co., LTD in Shenzhen city | GDY269-WZ-90 | 4×165KW | 2015 | |
66 | Xiajia hydropower station of Linyun power station subsidiary company in Guangxi province | GD007-WZ-90 | 1×1000KW | 2007 | Straight league |
67 | Laijiashan hydropower station in Nanzheng county | GDY269-WZ-80 | 1×160KW | 2013 | SFW160-12/740 |
68 | Mingyang hydraulic turbine Co.,LTD in Liuzhou city | GD008-WZ-60 | 1×100KW | 2011 | Straight league |
69 | Xiashan reservoir in Shandong province | GD007-WZ-60 | 2×150KW | 2006 | Straight league |
Jiangsu Aerospace Hydraulic Equipments Co.,Ltd(JAHEC)
ADD:No.8 Bosideng Ave. Gaoyou, Jiangsu Province P.R.C.
TEL/FAX:+86 514-80955126
HTTP//:aerospace.en.made-in-china.com
Address:
8 Bosideng Ave, Yangzhou, Jiangsu, China
Business Type:
Manufacturer/Factory
Business Range:
Industrial Equipment & Components, Manufacturing & Processing Machinery, Security & Protection, Service, Tools & Hardware, Transportation
Management System Certification:
ISO 9001, ISO 14001, OHSAS/ OHSMS 18001
Company Introduction:
Jiangsu Aerospace Hydraulic Equipments Co., Ltd. (formerly State-owned Gaoyou Water Pump Factory), a state grade II enterprise and the state high-tech enterprise, is the professional manufacturer of large-scale water pump and hydro turbine unit, designated by the former ministry of machinery industry; And a key enterprise of Jiangsu province machinery industry. Now it becomes the enterprise under the No. 6 Institute of China Aerospace Science and Technology Group, with strong supports of the application technology of aerospace fluid technology and materials. Our company is the domestic large production base with the first class comprehensive ability for design and manufacturing of medium and large pump, hydro-equipments.
The main products of the company: Medium-sized and large series axial flow pump and mixed flow pump (full adjustable, semi-regulation); Medium and large series of axial flow, mixed flow, tubular Hydro Generating Units; Open series centrifugal pump, mixed flow pump, the mobile pumping station and other industrial, municipal pumps.
The company covers an area of 20 hectares, has the modern industrial workshops of 45, 000 square meters, equipped with large-scale manufacturing and CNC processing center at the leading position among the same field in China. The Company has Hydraulic Machinery Research Institute and the hydraulic test center, for research and developing on high quality complete sets of hydraulic machinery. The quality system passed the ISO9002 international quality certification. The company has is qualified of import and export business. Large scale pump and turbine generator units, has received the awards of the National Science Conference, the pump research award of the National South-North Water Diversion Project, and national and provincial science and technology progress awards.
The company is located in Economic Development Zone of Gaoyou City, Jiangsu Province, China, close to the Beijing-Shanghai Expressway, Beijing- Shanghai High-speed Railway, Yangzhou Airports, the traffic is convenient. Warmly welcome friends from home and abroad to visit and instruct us.